Mon–Fri 9:00–18:00 · CST (UTC+8) · Shandong, China
Case Study · Energy Storage / Microgrid

Microgrid PCS Busbar: Flexible Stack Interconnect for 5 MWh Island Storage

PacificGrid Micro, an Australian integrator of remote and island microgrids, engaged SHANYUAN in 2025 for the battery-stack interconnects and PCS DC-link busbars of its 5 MWh-class storage containers. The flexible laminated stack interconnect — 800 A per string with 2% thermal balance across parallel strings — shipped with the first 3.2 MWh island project delivered on schedule in 2026.

ByAiko Tanaka Energy Storage / Microgrid Customer Case Study
Customer & Project

Project at a Glance

PacificGrid Micro Pty Ltd Energy Storage / Microgrid Australia · Remote and island microgrids Microgrid battery PCS and flexible stack busbar Delivered 2025–2026

This case study is published as a representative engineering project. The product photograph and released drawing are illustrative of the delivered part; exact dimensions are covered by the customer's non-disclosure agreement.

Engineering Drawings

Released Drawing

Engineering drawing for PacificGrid Micro — Microgrid battery PCS and flexible stack busbar
Released drawing excerpt

Customer drawings are treated as confidential; excerpts shown here are provided with permission and illustrate the layer stack, terminal layout and dielectric boundaries of the delivered part.

Product Photograph

The Delivered Part

Laminated busbar delivered for PacificGrid Micro — Microgrid battery PCS and flexible stack busbar
Representative product photograph of the delivered laminated busbar — insulated stack, terminals and dielectric finish as released for production.
Specifications

Project Parameters

Customer & platformPacificGrid Micro 5 MWh-class storage container, 800 V DC bus
Busbar typeFlexible laminated stack interconnect + rigid PCS DC-link busbar
Dielectric systemPET film + flexible insulation, 2.0 kV hi-pot
Current rating800 A per string, 1000 A 30 min
Thermal balance2% current balance across parallel strings, verified by IR imaging
Temperature riseΔT 25 °C at rated current, 50 °C ambient
TerminalsM8 studs, flexible laminations at interconnect ends
DeliveryFirst 3.2 MWh island project on schedule
Quantified result800 A, 2% thermal balance, 25 °C ΔT, on-schedule island delivery

PacificGrid Micro, an Australian integrator of remote and island microgrids, engaged SHANYUAN in 2025 for the battery-stack interconnects and PCS DC-link busbars of its 5 MWh-class storage containers. The flexible laminated stack interconnect — 800 A per string with 2% thermal balance across parallel strings — shipped with the first 3.2 MWh island project delivered on schedule in 2026.

The challenge: thermal balance across parallel battery strings

PacificGrid's 5 MWh-class containers series up to 18 battery strings in parallel on an 800 V DC bus. The previous interconnect — bolted copper bars plus flexible cable links — produced visible hot strings in thermal imaging: resistance differences between joints caused some strings to carry more than their share of current, accelerating degradation of those modules.

The customer specified a stack interconnect with controlled joint resistance per string (target 2% current imbalance at full load), a flexible section to absorb module expansion, and a PCS-side DC-link busbar that keeps the inverter's commutation loop tight. Current-sharing design guidance from our resources set the joint-resistance budget.

The project profile matches the energy storage application page and the microgrid busbar article.

The solution: flexible laminated stack interconnects with matched resistance

Each string interconnect uses a flexible laminated stack — copper laminations insulated with PET film and bonded at both ends — so the interconnect flexes with the battery module's thermal expansion while keeping a rigid bolted connection at the bus. The flexible insulated busbar product family carries this construction.

Joint resistance is matched per string during production: each interconnect is trimmed to hit a 0.45 mΩ ± 5% target, verified with a four-wire meter. The result is a 2% current balance across the 18 strings, confirmed by IR imaging at full load on the first container.

The PCS DC-link busbar uses the interleaved stack from the inverter DC-link busbar range, keeping the inverter commutation loop at 9 nH for the SiC power stage.

Thermal, mechanical and island-logistics engineering

Temperature-rise testing at 800 A in a 50 °C container ambient measured 25 °C rise with the hot spot at the string terminations — inside the 28 °C budget. The thermal management guide documents the container airflow assumptions.

Mechanical qualification covered the container's road and sea transport to the island site: vibration per IEC 60721-3-2, plus 2000 thermal cycles −20 °C to +60 °C on the flexible section. The flexible vs rigid selection guide explains when the flexible construction is the right choice.

Because the site is a remote island, every interconnect shipped pre-torqued with a torque-stripe audit and a per-part hi-pot certificate — no field torque decisions. The long-duration storage article covers the system context.

Delivery and commissioning

The first 3.2 MWh island project received all stack interconnects and PCS busbars in a single shipment, commissioned on schedule in 2026. The quality laboratory issued per-batch dossiers covering joint resistance, hi-pot and thermal-rise data, which the project's independent commissioning engineer accepted without additional testing.

Commissioning IR imaging at full load confirmed the 2% thermal balance across all 18 strings — the first container in the customer's fleet to meet the target without field rework. The factory tour shows the flexible lamination station used for these interconnects.

The second container project is now in production, sized at the full 5 MWh with the same interconnect platform.

Quantified results

The delivered interconnects met every target: 800 A per string with 25 °C rise in 50 °C ambient, 2% current balance across 18 parallel strings, 2000 thermal cycles on the flexible section, and on-schedule commissioning of the island project.

The customer reports that the matched-resistance interconnect eliminated the hot-string issue entirely, and the pre-torqued delivery removed field torque decisions on a site with limited tooling access. The global storage market article and the supplier evaluation guide give the procurement context behind this long-term award.

For microgrid and ESS integrators, the energy storage application page, the high-current battery module busbar and the engineering contact form are the practical entry points.

Thermal balance2% across 18 strings
String current800 A continuous
ΔT at rating25 °C @ 50 °C ambient
Delivery3.2 MWh island project on schedule
FAQ

Frequently asked questions

Why use a flexible interconnect between battery strings?
The flexible laminated section absorbs thermal expansion of the battery modules while keeping a rigid, torque-controlled bolted connection at the bus. It also simplifies assembly in a confined container.
How is 2% current balance achieved?
Every interconnect is trimmed during production to a 0.45 mΩ ± 5% joint-resistance target, verified with a four-wire meter, so all parallel strings see matched resistance. IR imaging at full load confirms the balance.
What happens on remote sites with limited tooling?
All interconnects ship pre-torqued with a torque-stripe audit and per-part hi-pot certificate, so commissioning requires no field torque decisions.
Related

Continue reading

C&I Energy Storage Goes Mainstream: Busbar Lessons from a 41.8 GWh Year
Energy Storage

C&I Energy Storage Goes Mainstream: Busbar Lessons from a 41.8 GWh Year

Commercial and industrial storage is the fastest-growing segment of the 2026 bat

Read article
Long-Duration Storage Hits 64% of New China Capacity: What CAES and Flow Projects Demand from DC Busbars
Energy Storage

Long-Duration Storage Hits 64% of New China Capacity: What CAES and Flow Projects Demand from DC Busbars

The storage industry's next wave is measured in hours, not megawatt-hours. China

Read article
Aiko Tanaka
Aiko TanakaApplication Engineering Manager

Aiko Tanaka is application engineering manager at SHANYUAN, with 11 years in applying laminated busbars to data centres, energy storage and new-energy systems. She leads application selection, custom-profile development and project delivery, and holds a B.Eng. in Electrical Engineering from the Univ

Data CenterEnergy StorageApplication Engineering
See Full Bio

Designing a busbar for this application?

Send the current profile, voltage class and terminal types — our engineers reply within one business day.