Case Study · Renewable Energy / Wind

Wind Converter DC-Link: Capacitor-Bank Busbar Halves Module Voltage Stress

Nordwind Power Systems, a Danish converter manufacturer serving European onshore and offshore wind projects, contracted SHANYUAN in late 2025 to supply the DC-link capacitor-bank busbar for its 6 MW converter platform. The 6-layer laminated design reduced effective series inductance by 43%, held temperature rise to 24 °C at 2400 A, and included 4000 m altitude derating — a requirement driven by Andean wind projects.

ByElena Vasquez Renewable Energy / Wind Customer Case Study
Customer & Project

Project at a Glance

Nordwind Power Systems A/S Renewable Energy / Wind Denmark · Delivered to European wind farms Wind turbine converter DC-link and capacitor-bank busbar Delivered 2025–2026

This case study is published as a representative engineering project. The product photograph and released drawing are illustrative of the delivered part; exact dimensions are covered by the customer's non-disclosure agreement.

Engineering 도면s

Released 도면

Engineering drawing for Nordwind Power — Wind turbine converter DC-link and capacitor-bank busbar
Released drawing excerpt

Customer drawings are treated as confidential; excerpts shown here are provided with permission and illustrate the layer stack, terminal layout and dielectric boundaries of the delivered part.

Product Photograph

The Delivered Part

Laminated busbar delivered for Nordwind Power — Wind turbine converter DC-link and capacitor-bank busbar
Representative product photograph of the delivered laminated busbar — insulated stack, terminals and dielectric finish as released for production.
Specifications

Project Parameters

Customer & platformNordwind Power 6 MW wind converter, 1500 V DC-link, 2400 A continuous
Busbar type6-layer laminated DC-link + capacitor-bank busbar, C11000 copper
Dielectric systemNomex 410 + epoxy edge, PD-free to 2.4 kV, 4.8 kV hi-pot
ESL reduction43% lower effective series inductance vs the previous solid-copper layout
정격 전류2400 A continuous, 100% ripple current on capacitor section
온도 상승ΔT 24 °C at rated current, measured on capacitor tabs
TerminalsBlade terminals for film capacitors, M10 studs for IGBT modules, silver-plated
Altitude rating4000 m derating per IEC 60068-2-13, creepage extended 30%
Quantified result43% lower ESL, 24 °C ΔT, PD-free to 2.4 kV, 4000 m altitude rated

Nordwind Power Systems, a Danish converter manufacturer serving European onshore and offshore wind projects, contracted SHANYUAN in late 2025 to supply the DC-link capacitor-bank busbar for its 6 MW converter platform. The 6-layer laminated design reduced effective series inductance by 43%, held temperature rise to 24 °C at 2400 A, and included 4000 m altitude derating — a requirement driven by Andean wind projects.

The challenge: ripple current and module voltage stress in a 6 MW converter

Nordwind's 6 MW converter platform uses a three-level NPC topology with a 1500 V DC-link. During commissioning of the first prototypes, the engineering team measured higher-than-expected voltage ripple at the IGBT modules and saw elevated capacitor temperatures at full load. The root cause traced to the solid-copper busbar layout: the capacitor-bank connections were too far from the module commutation loops, adding series inductance that amplified ripple current stress.

The customer asked SHANYUAN to design a replacement DC-link busbar with two hard requirements: keep the existing mechanical envelope, and reduce effective series inductance enough to bring module voltage stress back inside the silicon derating curve. Our response started with a review of their released drawings against the low-inductance design guide, and a laminated busbar design guide DFM pass on layer count and terminal placement.

Ripple-current data from the customer's power-stage tests was used to size the copper section and confirm the capacitor connection scheme before any tooling was committed.

The solution: six interleaved layers with a dedicated capacitor section

The final design uses six interleaved copper layers — three positive and three negative — arranged so that every capacitor tab sits directly above the corresponding IGBT module commutation loop. This stacked geometry cancels magnetic flux between layers and shortens the current path for each capacitor individually.

On the test bench, effective series inductance fell by 43% against the old solid-copper layout, and module voltage ripple at full switching frequency dropped into the silicon's safe operating area. The capacitor bank busbar product family documents this layer-interleaving pattern, and the power electronics busbar range carries the equivalent DC-link configurations.

Blade terminals for the film capacitors were machined with a 0.03 mm flatness target so that each capacitor connection carries its share of the ripple current evenly; joint resistance per tab was held below 40 μΩ.

Altitude, dielectric and thermal engineering

Because Nordwind ships to high-altitude wind farms, the busbar had to be rated to 4000 m. Per IEC 60068-2-13, air pressure at 4000 m is roughly 61% of sea level, so creepage distances were extended by 30% and the partial-discharge test voltage was derated accordingly. The insulation system — Nomex 410 film with epoxy edge sealing — remains PD-free to 2.4 kV at sea level and 2.0 kV at altitude.

Dielectric selection followed the design guide voltage-class rules, and the full PD test method is documented in the partial-discharge resource. Thermal testing measured 24 °C temperature rise at 2400 A in a 50 °C ambient chamber, with the hot spot on the capacitor tabs; forced-air cooling in the converter cabinet holds operating temperature comfortably inside the PET/Nomex rating.

Creepage and clearance tables used for this project are the same reference values published in the ampacity chart and the thermal management guide.

Production and qualification

Prototypes were delivered in week six, and the customer's power-stage test bench confirmed the ESL and ripple improvements within the first two test days. Qualification followed a 12-week PPAP plan: 4.8 kV hi-pot, 500 thermal cycles from −40 °C to +105 °C, and vibration per IEC 61373 category 2 for turbine-mounted electronics.

Series production runs in batches of 120 parts with 100% hi-pot and inductance scan per part, mirroring the process used for our other solar and wind applications. The quality laboratory issues a per-batch test dossier covering ESL, PD and thermal-rise measurements, which Nordwind's quality team accepts without additional audits.

The customer's procurement team also used our supplier evaluation guide during the initial shortlisting; the full wind converter busbar demand article explains why converter OEMs are moving to laminated DC-links in this power class.

Quantified results

The delivered busbar met every target on the customer's test bench: 43% lower effective series inductance, 24 °C temperature rise at 2400 A, PD-free to 2.4 kV at sea level and 2.0 kV at 4000 m altitude, and joint resistance below 40 μΩ per capacitor tab.

Module voltage stress returned inside the silicon derating curve at full switching frequency, and the converter passed type testing in the first attempt — the customer reported that the busbar change removed the need for a module derating step that had been planned for the 4000 m variant.

For engineers designing wind or PV converter DC-links, the solar and wind application page, the low-inductance guide and the SHANYUAN engineering desk are the fastest route to a first-pass layout.

ESL reduction43% vs solid-copper layout
Current2400 A continuous
ΔT at rating24 °C @ 50 °C ambient
Altitude rating4000 m, creepage +30%
자주 묻는 질문

Frequently asked questions

Why use Nomex instead of PET film on a wind converter DC-link busbar?
The 1500 V three-level topology needs a higher withstand margin than a standard 800 V platform, and the customer specified 4000 m altitude operation. Nomex 410 gives higher short-term thermal margin and better dielectric consistency for the extended creepage design.
How did the layer interleaving reduce module voltage stress?
Six interleaved positive/negative layers cancel loop flux inside the stack and put each capacitor tab directly above the module commutation loop, shortening the current path per capacitor. Effective series inductance fell 43%, which reduced ripple-induced voltage stress on the IGBT modules.
What altitude derating was applied?
Per IEC 60068-2-13, creepage was extended 30% and PD test voltage derated for 4000 m air pressure. The part remains PD-free to 2.4 kV at sea level and 2.0 kV at altitude.
관련 자료

계속 읽기

15MW 시대의 해상 풍력이 컨버터 버스바 요구사항을 다시 쓴다
Power Electronics

15MW 시대의 해상 풍력이 컨버터 버스바 요구사항을 다시 쓴다

더 큰 터빈은 더 큰 파워 스택을 의미하고, 그것이 나셀 내 DC링크 버스바를 물리적으로 집중시킵니다. 15MW 풍력 컨버터가 절연 버스바 요구

기사 읽기
ESS PCS DC-link 버스바 2026
에너지 저장

ESS PCS DC-link 버스바 2026

글로벌 BESS가 100GW 시대에 접어들며 PCS DC-link 버스바가 대용량화됩니다.

기사 읽기
Elena Vasquez
Elena Vasquez전력전자 응용 엔지니어

Elena Vasquez는 적층 버스바를 EV 인버터, 충전 시스템, 에너지 저장 PCS에 통합한 경력 10년의 전력전자 응용 엔지니어입니다. 저인덕턴스 DC-링크 설계, EMC 동작, 컨버터 패키징을 전문으로 합니다. 마드리드 폴리테크닉 대학교에서 전기공학 학사 학위를 취득했습니다. 인버터 버스바 선정, 기생 인덕턴스, SiC 레이아웃에 대해 집필합니다.

EV 인버터EMCPCS 통합
전체 프로필 보기

이 애플리케이션용 버스바를 설계 중이신가요?

전류 프로파일, 전압 등급, 단자 유형을 보내주세요 — 엔지니어가 영업일 1일 내 답변합니다.