Case Study · Renewable Energy / Wind

Wind Converter DC-Link: Capacitor-Bank Busbar Halves Module Voltage Stress

Nordwind Power Systems, a Danish converter manufacturer serving European onshore and offshore wind projects, contracted SHANYUAN in late 2025 to supply the DC-link capacitor-bank busbar for its 6 MW converter platform. The 6-layer laminated design reduced effective series inductance by 43%, held temperature rise to 24 °C at 2400 A, and included 4000 m altitude derating — a requirement driven by Andean wind projects.

ByElena Vasquez Renewable Energy / Wind Customer Case Study
Customer & Project

Project at a Glance

Nordwind Power Systems A/S Renewable Energy / Wind Denmark · Delivered to European wind farms Wind turbine converter DC-link and capacitor-bank busbar Delivered 2025–2026

This case study is published as a representative engineering project. The product photograph and released drawing are illustrative of the delivered part; exact dimensions are covered by the customer's non-disclosure agreement.

Engineering Plans

Released Plan

Engineering drawing for Nordwind Power — Wind turbine converter DC-link and capacitor-bank busbar
Released drawing excerpt

Customer drawings are treated as confidential; excerpts shown here are provided with permission and illustrate the layer stack, terminal layout and dielectric boundaries of the delivered part.

Product Photograph

The Delivered Part

Laminated busbar delivered for Nordwind Power — Wind turbine converter DC-link and capacitor-bank busbar
Representative product photograph of the delivered laminated busbar — insulated stack, terminals and dielectric finish as released for production.
Specifications

Project Parameters

Customer & platformNordwind Power 6 MW wind converter, 1500 V DC-link, 2400 A continuous
Busbar type6-layer laminated DC-link + capacitor-bank busbar, C11000 copper
Dielectric systemNomex 410 + epoxy edge, PD-free to 2.4 kV, 4.8 kV hi-pot
ESL reduction43% lower effective series inductance vs the previous solid-copper layout
Courant nominal2400 A continuous, 100% ripple current on capacitor section
ÉchauffementΔT 24 °C at rated current, measured on capacitor tabs
TerminalsBlade terminals for film capacitors, M10 studs for IGBT modules, silver-plated
Altitude rating4000 m derating per IEC 60068-2-13, creepage extended 30%
Quantified result43% lower ESL, 24 °C ΔT, PD-free to 2.4 kV, 4000 m altitude rated

Nordwind Power Systems, a Danish converter manufacturer serving European onshore and offshore wind projects, contracted SHANYUAN in late 2025 to supply the DC-link capacitor-bank busbar for its 6 MW converter platform. The 6-layer laminated design reduced effective series inductance by 43%, held temperature rise to 24 °C at 2400 A, and included 4000 m altitude derating — a requirement driven by Andean wind projects.

The challenge: ripple current and module voltage stress in a 6 MW converter

Nordwind's 6 MW converter platform uses a three-level NPC topology with a 1500 V DC-link. During commissioning of the first prototypes, the engineering team measured higher-than-expected voltage ripple at the IGBT modules and saw elevated capacitor temperatures at full load. The root cause traced to the solid-copper busbar layout: the capacitor-bank connections were too far from the module commutation loops, adding series inductance that amplified ripple current stress.

The customer asked SHANYUAN to design a replacement DC-link busbar with two hard requirements: keep the existing mechanical envelope, and reduce effective series inductance enough to bring module voltage stress back inside the silicon derating curve. Our response started with a review of their released drawings against the low-inductance design guide, and a laminated busbar design guide DFM pass on layer count and terminal placement.

Ripple-current data from the customer's power-stage tests was used to size the copper section and confirm the capacitor connection scheme before any tooling was committed.

The solution: six interleaved layers with a dedicated capacitor section

The final design uses six interleaved copper layers — three positive and three negative — arranged so that every capacitor tab sits directly above the corresponding IGBT module commutation loop. This stacked geometry cancels magnetic flux between layers and shortens the current path for each capacitor individually.

On the test bench, effective series inductance fell by 43% against the old solid-copper layout, and module voltage ripple at full switching frequency dropped into the silicon's safe operating area. The capacitor bank busbar product family documents this layer-interleaving pattern, and the power electronics busbar range carries the equivalent DC-link configurations.

Blade terminals for the film capacitors were machined with a 0.03 mm flatness target so that each capacitor connection carries its share of the ripple current evenly; joint resistance per tab was held below 40 μΩ.

Altitude, dielectric and thermal engineering

Because Nordwind ships to high-altitude wind farms, the busbar had to be rated to 4000 m. Per IEC 60068-2-13, air pressure at 4000 m is roughly 61% of sea level, so creepage distances were extended by 30% and the partial-discharge test voltage was derated accordingly. The insulation system — Nomex 410 film with epoxy edge sealing — remains PD-free to 2.4 kV at sea level and 2.0 kV at altitude.

Dielectric selection followed the design guide voltage-class rules, and the full PD test method is documented in the partial-discharge resource. Thermal testing measured 24 °C temperature rise at 2400 A in a 50 °C ambient chamber, with the hot spot on the capacitor tabs; forced-air cooling in the converter cabinet holds operating temperature comfortably inside the PET/Nomex rating.

Creepage and clearance tables used for this project are the same reference values published in the ampacity chart and the thermal management guide.

Production and qualification

Prototypes were delivered in week six, and the customer's power-stage test bench confirmed the ESL and ripple improvements within the first two test days. Qualification followed a 12-week PPAP plan: 4.8 kV hi-pot, 500 thermal cycles from −40 °C to +105 °C, and vibration per IEC 61373 category 2 for turbine-mounted electronics.

Series production runs in batches of 120 parts with 100% hi-pot and inductance scan per part, mirroring the process used for our other solar and wind applications. The quality laboratory issues a per-batch test dossier covering ESL, PD and thermal-rise measurements, which Nordwind's quality team accepts without additional audits.

The customer's procurement team also used our supplier evaluation guide during the initial shortlisting; the full wind converter busbar demand article explains why converter OEMs are moving to laminated DC-links in this power class.

Quantified results

The delivered busbar met every target on the customer's test bench: 43% lower effective series inductance, 24 °C temperature rise at 2400 A, PD-free to 2.4 kV at sea level and 2.0 kV at 4000 m altitude, and joint resistance below 40 μΩ per capacitor tab.

Module voltage stress returned inside the silicon derating curve at full switching frequency, and the converter passed type testing in the first attempt — the customer reported that the busbar change removed the need for a module derating step that had been planned for the 4000 m variant.

For engineers designing wind or PV converter DC-links, the solar and wind application page, the low-inductance guide and the SHANYUAN engineering desk are the fastest route to a first-pass layout.

ESL reduction43% vs solid-copper layout
Current2400 A continuous
ΔT at rating24 °C @ 50 °C ambient
Altitude rating4000 m, creepage +30%
FAQ

Frequently asked questions

Why use Nomex instead of PET film on a wind converter DC-link busbar?
The 1500 V three-level topology needs a higher withstand margin than a standard 800 V platform, and the customer specified 4000 m altitude operation. Nomex 410 gives higher short-term thermal margin and better dielectric consistency for the extended creepage design.
How did the layer interleaving reduce module voltage stress?
Six interleaved positive/negative layers cancel loop flux inside the stack and put each capacitor tab directly above the module commutation loop, shortening the current path per capacitor. Effective series inductance fell 43%, which reduced ripple-induced voltage stress on the IGBT modules.
What altitude derating was applied?
Per IEC 60068-2-13, creepage was extended 30% and PD test voltage derated for 4000 m air pressure. The part remains PD-free to 2.4 kV at sea level and 2.0 kV at altitude.
Connexes

Continuer la lecture

L'ère des 15 MW de l'éolien offshore réécrit les exigences des barres de convertisseur
Power Electronics

L'ère des 15 MW de l'éolien offshore réécrit les exigences des barres de convertisseur

Des turbines plus grandes signifient des stacks de puissance plus grands, et c'e

Lire l’article
PCS de stockage réseau en 2026 : bus DC 1500 V, efficacité SiC et la barre DC-link
Stockage d'énergie

PCS de stockage réseau en 2026 : bus DC 1500 V, efficacité SiC et la barre DC-link

BloombergNEF voit 158-188 GW de nouveau stockage d'énergie en 2026. Les platefor

Lire l’article
Elena Vasquez
Elena VasquezIngénieure d'application en électronique de puissance

Elena Vasquez est ingénieure d'application en électronique de puissance avec 10 ans d'expérience dans l'intégration de barres omnibus laminées dans les onduleurs VE, les systèmes de charge et les PCS de stockage d'énergie. Elle se spécialise dans la conception de liaisons DC à fa

Onduleur VECEMIntégration PCS
Voir la bio complète

Vous concevez une barre omnibus pour cette application ?

Envoyez le profil de courant, la classe de tension et les types de bornes — nos ingénieurs répondent en un jour ouvré.