Copper busbar current ratings by cross-section, plus the derating factors that decide whether those numbers survive in your enclosure.
| Cross-section (mm) | Area (mm²) | DC current (A) | AC 60 Hz (A) |
|---|---|---|---|
| 10 × 3 | 30 | ~150 | ~150 |
| 15 × 3 | 45 | ~200 | ~200 |
| 20 × 3 | 60 | ~250 | ~250 |
| 25 × 3 | 75 | ~300 | ~295 |
| 30 × 5 | 150 | ~450 | ~440 |
| 40 × 5 | 200 | ~550 | ~535 |
| 50 × 5 | 250 | ~650 | ~630 |
| 60 × 6 | 360 | ~800 | ~770 |
| 80 × 6 | 480 | ~1000 | ~960 |
| 100 × 6 | 600 | ~1150 | ~1100 |
Two things to read out of this table before using it. First, the AC and DC columns are close at 50/60 Hz because skin depth in copper at that frequency exceeds every bar thickness listed here; the columns only diverge as frequency rises. Second, these numbers assume a single bar in open air — stacked or packed bars derate quickly, per the factors below.
Cross-sections are reference values for planning, not release specifications: every released part is sized against your actual mounting and ambient. Our standard copper is C11000; when aluminum is chosen for weight or cost, it needs its own sizing — see copper vs aluminum busbar conductors.
One more reason the table uses a fixed 30 °C rise: temperature is what ultimately limits the part. Copper resistance rises about 0.4% per °C, so a conductor running at 100 °C dissipates roughly 40% more heat for the same current than one at 20 °C. A 30 °C rise above 40 °C ambient lands the conductor near 70 °C — comfortably inside a 105 °C dielectric system with margin left. If your enclosure already runs hot, you are buying margin you cannot use; size to the actual ambient instead. Every released part passes hipot, insulation-resistance and continuity checks under our in-house busbar testing process, with batch records supplied on request.
| Factor | Effect | Typical derate |
|---|---|---|
| Ambient temperature | Higher ambient raises conductor temperature | −1% per °C above 40 °C |
| Bundled bars | Adjacent conductors heat each other | −10 to −20% depending on spacing |
| Enclosed / still air | Reduced convection | −10 to −25% |
| Altitude | Thinner air cools less effectively | −1% per 200 m above 1000 m |
| AC frequency | Skin and proximity effect push current to surfaces | Material above ~1 kHz; consult us |
| Pulsed current | Thermal mass absorbs short pulses | Can allow higher peaks than continuous |
How the factors combine matters more than any single row. Derating multiplies: a part rated 450 A in free air at 40 °C, mounted in a sealed cabinet (about −20%) at a 60 °C ambient (about −20% from temperature), lands near 450 × 0.8 × 0.8 ≈ 290 A — not 450 minus 40. Treat the rows as independent multipliers and stack them.
Two further factors decide real designs less often but more heavily:
There is one ceiling the multiplier table cannot express: the dielectric temperature limit. The copper may survive 120 °C, but a 105 °C film system does not. In practice you cross-check the computed conductor temperature against the dielectric class — a 105 °C system wants the conductor near 70–80 °C, while a 130 °C high-temperature system lets the same copper carry roughly 20–30% more current. Choosing the dielectric class is therefore part of current sizing, not a separate step. Lifetime implications are covered in busbar thermal management.
The mechanism is symmetry. Where positive and negative terminals exit the stack side by side, their magnetic fields cancel and current distributes evenly across the parallel layers. Where one terminal sits offset, or layers enter from different edges, impedance differences — tiny at DC, significant at the switching frequency — push more current through one layer. That layer hits its temperature limit first, while the cooler layer's copper was bought for nothing.
Rules we apply in DFM:
High frequency changes the picture again. Above roughly 1 kHz, skin and proximity effects push current to the surfaces of the conductor, so a single thick bar wastes its center. A laminated stack of thinner layers with overlapping planes behaves better electrically at these frequencies than the same cross-section in one plate — another reason the stacked geometry is preferred for DC-link paths, not just for terminal layout.
Ampacity tables hide the physics: a current rating is really a temperature-limit calculation. Treat heat flow like an electrical circuit — Ohm's law in thermal clothing:
Conduction inside the stack is not the bottleneck. Copper spreads heat extremely well — thermal conductivity of roughly 370–400 W/m·K — and even the 0.2–0.4 mm dielectric film drops only about 0.5–1 °C across itself. The bar's own mass averages the heat over its whole surface.
Convection to ambient dominates natural cooling. A flat, thin laminate presents a very large surface for its volume — an inherent advantage over a round cable bundle. Reference heat-flux capability: natural convection about 5 W/dm²; forced air with fans about 50 W/dm². Orientation shifts the result too: vertical mounting typically improves heat removal by roughly 20% over horizontal.
Radiation contributes more than people expect. Bare polished copper radiates almost nothing (emissivity about 0.03); a painted or film-laminated outer surface reaches about 0.9. For a naturally cooled part, radiation accounts for roughly 40% of total heat removal — which is why a black-painted busbar can run about 25 °C cooler than the same bar left bare, counter-intuitive as it sounds.
Busbar conduction losses are typically 10–100 W, so natural air cooling almost always suffices; you do not need to fan the bar itself, though neighboring fan cooling adds margin. The full mechanism, including measurement practice, is in busbar thermal management.
A quick worked example makes the surface budget tangible. With a 30 °C maximum rise and an overall heat-transfer coefficient near 20 W/m²·K on both faces, a naturally cooled laminate sheds about 6 W per square decimeter of surface. A 25 × 40 cm bar therefore dissipates roughly 60 W without any fan — comfortably above the 10–100 W loss range typical of these parts. Forced air raises the heat-transfer coefficient to 50–100 W/m²·K, roughly 5–10 times the natural value, and allows 2–3 times the current on the same copper. In practice the airflow around a power stack already adds this margin, which is why busbar cooling calculations usually start from natural convection and stop there.
Continuous rating asks what the bar can carry forever. Pulsed duty asks something else: how much heat the copper can absorb before its temperature limit is reached. Copper mass is a heat reservoir — short, high-current pulses dump energy into the body faster than the surface can shed it, and the rise depends on pulse duration and repetition, not just RMS current.
Reference practice for sizing pulses:
Pulse scenarios in real designs include inrush into DC-link capacitors, motor starting currents, and charge-discharge peaks in storage systems. If your current profile is pulsed, send us the pulse width, peak and repetition rate; the thermal-mass calculation is documented with the sizing sheet.
Contrast the two regimes on the same part: a 30 × 5 mm copper bar rated about 450 A continuously in free air may comfortably carry 900–1000 A for a fraction of a second during a motor start, because the heat has no time to reach the surface. Hold that same 900 A for a minute, and the same bar overheats — the reservoir has filled and continuous rules take over. Knowing which regime you are in is half the sizing problem. Thermal mass also decides fault behavior: a short-circuit peak of several kiloamperes for a few cycles does not overheat a well-sized bar, which is one more reason conductor cross-section, not just continuous current, is documented in the release drawing.
The chart becomes useful once anchored to a duty cycle. Three reference configurations — typical planning values, to be verified per drawing:
| Application | Typical current window | Sizing starting point | Watch-out |
|---|---|---|---|
| EV traction inverter DC link | 300–500 A continuous; peaks 1.5–2× | 2–3 layers of 30–40 mm copper; pulsed peak sizing | Under-hood ambient ~105–125 °C; high-temp dielectric |
| Energy storage (BESS) converter | 200–800 A, near-continuous | Single stack 40–60 mm section, natural cooling | Container ambient up to 50 °C; long mission profile |
| Industrial / solar inverter DC link | 250–600 A with 1600 VDC class | Derated cross-section plus rigid inter-layer insulation | Altitude and partial-discharge control at 1600 VDC |
| Rail traction converter | 400–800 A, 1500–3000 VDC class | High-temperature 130 °C dielectric; rigid insulation per voltage class | 25-year service life; derating for reliability |
The rail row maps to our rail traction busbar page, where the environmental case — wide temperature swings, humidity, service continuity — drives a more conservative derate than any of the other applications.
These map to the field roles described in EV busbars, energy storage busbars and inverter busbars — each application page lists the thermal and electrical environment that drives the derate. The same sizing pattern recurs in EV charging station busbars — continuous rectifier-to-outlet distribution with low ripple — and in data center power distribution, where flat, low-profile planes carry rack-level DC with high reliability. In every case the continuous number from the chart is the starting line, not the final specification.
Then confirm the loop inductance of the selected geometry. Current capacity and inductance are optimized together, not separately — see low-inductance busbar design.
To run this process for you we need four things: the continuous current and any peak or pulse profile, the voltage class, the enclosure ambient and cooling mode, and the terminal types. With those, we return a recommended cross-section, layer count and dielectric choice, with the calculation documented alongside the quotation — typically within one business day. Values in the chart are planning references; every released part is computed against your drawing, and the quoted part always carries its sizing sheet.
Send the current profile, voltage class and installation conditions — we will size the busbar and document the calculation with your quotation.
Send the current profile, voltage class and installation conditions — we will size the busbar and document the calculation.