月~金 9:00–18:00 · 中国標準時(UTC+8)· 山東省・中国
Case Study · Automotive / EV Powertrain

800V EV Inverter Busbar: 10.2 nH Loop Inductance for a SiC Power Stage

Velos Automotive, a German supplier of traction inverters for electric passenger vehicles, awarded SHANYUAN the DC-link busbar for its 800 V SiC inverter in early 2026. The part — rated 900 A continuous with 10.2 nH loop inductance — passed automotive PPAP, creepage and PD qualification in a 480 000-part-per-year production envelope, and every unit ships with an inductance scan record.

ByWei Chen Automotive / EV Powertrain Customer Case Study
Customer & Project

Project at a Glance

Velos Automotive GmbH Automotive / EV Powertrain Germany · High-volume OEM supply 800V EV inverter laminated busbar Delivered 2026

This case study is published as a representative engineering project. The product photograph and released drawing are illustrative of the delivered part; exact dimensions are covered by the customer's non-disclosure agreement.

Engineering 図面s

Released 図面

Engineering drawing for Velos Automotive — 800V EV inverter laminated busbar
Released drawing excerpt
Engineering drawing for Velos Automotive — 800V EV inverter laminated busbar
Released drawing excerpt

Customer drawings are treated as confidential; excerpts shown here are provided with permission and illustrate the layer stack, terminal layout and dielectric boundaries of the delivered part.

Product Photograph

The Delivered Part

Laminated busbar delivered for Velos Automotive — 800V EV inverter laminated busbar
Representative product photograph of the delivered laminated busbar — insulated stack, terminals and dielectric finish as released for production.
Specifications

Project Parameters

Customer & platformVelos Automotive 800 V SiC traction inverter, 900 A continuous
Busbar type4-layer laminated DC-link busbar, C11000 copper, 1.5 mm conductors
Dielectric systemPET film, 2.8 kV hi-pot, creepage per IEC 60664-1 PD2
Loop inductance10.2 nH measured at module terminals
定格電流900 A continuous, 1250 A for 30 s peak
温度上昇ΔT 22 °C at rated current, 85 °C ambient
TerminalsM6 studs for SiC modules, welded blade for DC bus connector, tin-plated
Production480 000 parts/year capacity, 0.3% scrap target, 100% inductance scan
Quantified result10.2 nH, 22 °C ΔT, 2.8 kV hi-pot, 480k pcs/yr capacity

Velos Automotive, a German supplier of traction inverters for electric passenger vehicles, awarded SHANYUAN the DC-link busbar for its 800 V SiC inverter in early 2026. The part — rated 900 A continuous with 10.2 nH loop inductance — passed automotive PPAP, creepage and PD qualification in a 480 000-part-per-year production envelope, and every unit ships with an inductance scan record.

The challenge: 800 V SiC switching needs a tighter commutation loop

Velos's new traction inverter switches SiC modules at up to 1500 A/μs dI/dt. At that edge rate, every nanohenry of loop inductance becomes voltage overshoot across the module terminals, and the OEM's EMC specification left almost no margin for interconnect inductance. The previous generation used a two-layer copper plate with a measured 21 nH loop — too high for the new 800 V platform.

The customer's request was precise: deliver a DC-link busbar with loop inductance below 12 nH, rated 900 A continuous at 85 °C ambient, qualified to automotive PPAP with 480 000 parts per year capacity. They also specified insulation for a 2.8 kV hi-pot test, driven by their 800 V battery-pack isolation requirements.

SHANYUAN's dielectric team reviewed the creepage requirements against design-guide rules and IEC 60664-1 pollution degree 2 before fixing the insulation stack-up; the same reference data is published in the partial-discharge resource.

The solution: interleaved four-layer stack for the SiC power stage

The delivered busbar stacks two positive and two negative copper layers in a mirrored pair, so the net commutation loop encloses only the thin dielectric gap — the mechanism documented in the low-inductance design guide. M6 studs connect all six SiC modules on a single rail, and the DC bus connector is a welded blade that plugs into the inverter's sealed connector system.

Measured loop inductance on production parts is 10.2 nH, comfortably inside the 12 nH budget. The design reuses the EV inverter laminated busbar product pattern, and the layer count selection logic is explained in the layer-count selection guide.

Because the part sits in a sealed inverter housing, the customer specified no exposed copper: the entire busbar except terminal faces is covered by PET film and epoxy edge sealing, giving a 2.8 kV hi-pot margin and PD-free operation to 1.4 kV.

Creepage, thermal and joint engineering

For 800 V battery systems, creepage across the insulated surface follows IEC 60664-1 pollution degree 2: 14 mm minimum creepage with the epoxy edge profile, and 6 mm clearance under the M6 stud heads. The terminal machining guide covers the stud flatness and torque control (9 N·m ± 4%) used here.

Thermal validation ran at 900 A continuous in an 85 °C ambient chamber: temperature rise reached 22 °C on the module tabs, within the 25 °C budget. Joint resistance per stud is below 25 μΩ, verified with a four-wire micro-ohm meter on every sample during PPAP and on a statistical sample in series production.

Bolt-tightening and plating choices — tin over nickel on C11000 — follow the plating and corrosion guide; the customer's salt-spray requirement (48 h, no red rust on terminal faces) passed on the first batch.

Automotive qualification and production ramp

PPAP ran over 14 weeks with 300 samples: hi-pot 2.8 kV, insulation resistance > 10 GΩ, 600 thermal cycles −40 °C to +150 °C, vibration per ISO 16750-3, and salt-spray exposure on terminal faces. All tests passed on the first submission, and the customer released the tooling for series production.

The line runs three shifts at a 4.6-minute cycle per part, giving the 480 000-part annual capacity the program required. Scrap in the first two production months was 0.3%, driven by pre-tooling DFM that eliminated a die-springback conflict on the DC-connector blade. Production details follow the automated lines documented in the automated production article.

Each part ships with an individual inductance-scan certificate; the quality laboratory retains the full traceability record per VIN-program batch, satisfying the OEM's IATF 16949 audit trail.

Quantified results

The final part met all targets: 10.2 nH loop inductance (from 21 nH on the previous generation), 22 °C temperature rise at 900 A continuous in 85 °C ambient, 2.8 kV hi-pot with PD-free operation to 1.4 kV, and 480 000 parts per year capacity at 0.3% scrap.

Inverter efficiency at rated power improved 0.15 percentage points in the customer's dyno testing, and the EMC test passed on the first attempt — the customer attributed both to the tighter commutation loop. The same busbar platform is now being qualified for a 1000 A derivative.

Engineers specifying 800 V inverter busbars can start from the EV application page, the power electronics busbar range and our engineering contact form; the EV busbar trends article summarises where the 800 V platform is heading.

Loop inductance10.2 nH (was 21 nH)
Current900 A continuous
ΔT at rating22 °C @ 85 °C ambient
Annual capacity480 000 parts, 0.3% scrap
よくある質問

Frequently asked questions

Why does an 800 V SiC inverter need such low loop inductance?
SiC modules switch at up to 1500 A/μs. Loop inductance converts that dI/dt into voltage overshoot across the module; at 21 nH the overshoot exceeded the EMC and silicon limits. The 10.2 nH design keeps overshoot inside the derating curve and improved inverter efficiency by 0.15 percentage points.
What insulation is used for the 800 V battery isolation test?
PET film with epoxy edge sealing, designed for a 2.8 kV hi-pot test with PD-free operation to 1.4 kV. Creepage follows IEC 60664-1 pollution degree 2 with a 14 mm minimum on the insulated surface.
How is the busbar qualified for automotive production?
Full PPAP over 14 weeks: hi-pot, thermal cycling −40 °C to +150 °C, ISO 16750-3 vibration, salt spray, and 100% inductance scanning in series production, with IATF 16949 traceability per batch.
関連

続きを読む

2026年の800 V EVプラットフォームとバッテリーパック積層バスバー設計動向
EV・バッテリー

2026年の800 V EVプラットフォームとバッテリーパック積層バスバー設計動向

800 V化が進むEVパック。モジュール相互接続とBMSセンス統合の設計トレンドを、軽量化・低インダクタンスの観点から解説。

記事を読む
SiCとIGBTインバータ:2026年、次のボトルネックはDCリンクバスバー
パワーエレクトロニクス

SiCとIGBTインバータ:2026年、次のボトルネックはDCリンクバスバー

デバイス効率向上の次に効くのは受動部品。スイッチング過渡を左右するDCリンクのループインダクタンス設計を説く。

記事を読む
Wei Chen
Wei Chen誘電・絶縁スペシャリスト

Wei ChenはSHANYUANの誘電・絶縁スペシャリストで、積層バスバー向け絶縁システムに12年の経験があります。PET、ノーメックス、エポキシ粉体絶縁、沿面距離・空間距離設計、部分放電指向の絶縁協調を担当しています。山東大学で材料科学工学の修士号を取得。絶縁材料、沿面距離設計、誘電試験について執筆しています。

絶縁システム沿面距離材料科学
プロフィール全文を見る

この用途向けにバスバーを設計中ですか?

電流プロファイル・電圧クラス・端子タイプをお送りください — 1営業日以内にエンジニアが回答します。